At the Flumenthal hydropower plant in Switzerland, the existing 50-year-old fish ladder no longer fulfilled modern fish migration requirements. As part of a comprehensive ecological upgrade, Alpiq Hydro Aare AG is constructing a new 480-meter-long bypass channel to ensure
sustainable fish passage. BOHREX AG was commissioned to execute the vibration-free partial demolition of a 25-meter-long reinforced concrete riverside wall while the power plant remained fully operational. The structure measured 7 meters in height and 2.5 meters in thickness.

Key Technical Data

  • Wall dimensions: 25 m (length) × 7 m (height) × 2.5 m (thickness)
  • Concrete type: Reinforced concrete
  • Element weight: Up to 35 tons per section
  • Thickness reduction: From 2.5 m to 0.5–0.7 m along the full length
  • Wire installation: 80-meter diamond wire for underwater cutting
  • Special adaptation: Customized wire saw system in cooperation with Tyrolit Switzerland

Execution Highlights

Stage 1 – Controlled Wall Reduction
The wall was cut into precisely defined elements using high-precision diamond wire sawing. Each segment was limited to a maximum weight of 35 tons to comply with crane load capacities and ensure safe removal.

Stage 2 – Underwater Preparation
The project required detailed preparation for underwater operations, including guide drillings and partition cuts for submerged sections.

Stage 3 – Underwater Wire Sawing
A continuous 25-meter cut with a wall thickness ranging from 70–130 cm was executed underwater. The operation required the installation of an 80-meter diamond wire and close coordination with a professional diving team.

Stage 4 – Wall Openings & Precision Drilling
Three underwater wall openings were created on the exterior side. Precision drilling enabled the installation of temporary steel retention structures for the future collection channel.

Project Significance

This project demonstrates advanced planning, innovative vibration-free demolition techniques, and exceptional technical coordination under hydraulic constraints.
The successful execution ensured uninterrupted hydropower plant operations while meeting stringent environmental and occupational safety standards — highlighting BOHREX’s expertis in complex concrete cutting under extreme conditions.

This project was presented for the IACDS Diamond Award 2025. Read the full article in the IACDS Yearbook 2026 and stay tuned for the upcoming IACDS Yearbook 2027.